Even if an application for summary procedures has a real prospect of
success, what are the issues you need to consider when weighing the
benefits to be gained from a successful application for summary procedures
on the one hand and the uncertainties of time, cost and effort associated
with doing so on the other?
1. What do your contract and chosen rules say?
Whether or not arbitrators have the power to grant summary procedures in
a particular case depends on what the parties have agreed, at least in the
first instance.
In some (unusual) cases, parties may have included specific provisions in
the arbitration agreement itself. Notably, the arbitration clause in Travis Coal
Restructured Holdings LLC v Essar Global Fund Ltd [2014] EWHC 2510
(Comm) (which was found to authorise summary procedures) provided:
"The arbitrators shall have the discretion to hear and determine at
any stage of the arbitration any issue asserted by any party to be
dispositive of any claim or counterclaim, in whole or part…".
This sort of express language is, however, the exception rather than the
rule. Absent this degree of specificity in the arbitration clause, the question
shifts to the arbitral rules the parties have selected. A few sets of rules deal
with this issue explicitly, notably the Stockholm Chamber of Commerce
Rules (Article 39(1)), the ICSID Arbitration Rules (Rule 41(5)) and the
Singapore International Arbitration Centre Rules (Rule 29.1). There are
some differences in wording and approach. The SCC Rules give tribunals
the specific power to decide issues summarily and without taking every
procedural step that would otherwise have been undertaken, whereas the
ICSID and SIAC Rules allow a party to apply for the early dismissal of a
claim (or, under the SIAC Rules, a defence) on the basis that it is manifestly
without legal merit, or alternatively (under the SIAC Rules) that it is
manifestly outside the jurisdiction of the tribunal.
Other rules, while not addressing summary procedures explicitly, extend
broad case management powers to arbitrators, which may be sufficient
authority for a tribunal to order summary procedures. These include the ICC
Rules (Article 22.2), the LCIA Rules (Article 14), the UNCITRAL Arbitration
Rules (Article 17) and the ICDR Rules (Article 20.3). In the absence of
express provisions, however, there is room for significant debate as to what
procedures a tribunal can, and should, order.
In short, ask yourself: Is there any relevant language in the parties'
arbitration agreement? Which rules apply and what do they provide?
The more explicitly that summary procedures are authorised, the safer the
2. Where the rules are unclear, what will persuade a court to uphold an
award granted following a summary procedure?
There is little English case law on this point and Travis Coal is the high
water mark to date. The case concerned an ICC arbitration seated in New
York. Summary judgment was granted by the tribunal and the unsuccessful
party applied to a New York court to vacate the award, alleging failure of
due process. At the same time, the successful party sought to enforce the
award in England. Mr Justice Blair in the English Commercial Court
observed that summary judgment does not "necessarily amount to a denial
of due process" (paragraph 44), that the arbitration was conducted "in an
expeditious and cost-effective manner", that "each party [had] a fair
opportunity to present its case" and that "the procedure fell within [the
arbitration clause]" (paragraph 50). Therefore he concluded that, on the
facts of this case, the tribunal had not exceeded its powers. However, he
did not enter into the broader debate on the availability of summary
procedures in international arbitration.
In the case of Global International Reinsurance Co Ltd v TIG Insurance
Company 640 F. Supp. 2d 519 (2009), a New York court was asked to
vacate an arbitration award following a grant of partial summary judgment.
The parties' arbitration agreement provided that "[t]he arbitrator shall be
relieved of all judicial formality and shall not be bound by the strict rules of
law". Following a dispositive motion, the arbitrator received written
submissions and heard two days of oral argument from the parties. The
arbitrator granted summary judgment without discovery or an evidentiary
hearing and the losing party objected. The New York court refused to vacate
the award, ruling that the arbitration agreement had been explicit in relieving
the arbitrator from the strict rules of law and that the arbitrator had acted
within his powers: "the losing party got all that it bargained for when it
elected arbitration" (paragraph 1).
Both these cases indicate that where the rules are unclear, there are two
important areas you need to explore:
-
The nature of the application
What is the tribunal being asked to determine on a summary basis? Is it a
limited issue or substantially the whole dispute? How straightforward is the
underlying subject of the application? Some matters might be easier for a
tribunal to determine summarily than others.
-
The proposed procedure
What is the proposed procedure for dealing with the issue and is it
appropriate in the circumstances of the case? There is a spectrum of
potential procedures that can be ordered. In Travis Coal, the procedure
adopted was described by the judge as a "hybrid procedure" - it included an
oral hearing and limited cross-examination of witnesses.
Original Source: Hogan Lovells, Asia Talking Point: Construction and Engineering. December 2017
BACK TO NEWS INDEX